The short answer

If a neighbour starts work on a shared wall without serving notice, act quickly. Photograph everything, write to them asking them to stop and serve notice, and take advice before appointing a surveyor. Since a 2023 Court of Appeal ruling, an award made without a notice can be void, so the right route depends on what’s been built. An injunction is the backstop if they won’t stop.

Your neighbour started work without a party wall agreement, and the first you heard of it was a drill coming through the wall. It happens more often than you’d think. Builders start early, owners assume the paperwork can follow, and adjoining owners find out from the noise.

You have more power here than you might expect. The Party Wall etc. Act 1996 says notice must come before the work, and a court can stop work that’s gone ahead without it. But the route matters. A 2023 Court of Appeal case from Dagenham showed that the usual surveyor process doesn’t kick in when no notice has been served.

We act for adjoining owners in this position across London and Essex, and for building owners who started too soon and want to put it right. This guide covers what to do in the first week, if a retrospective agreement is possible and when going to court is worth the cost.

What should you do if a neighbour starts work without a party wall agreement?

Ask the neighbour to stop and serve notice, in writing, the same day. Then record the condition of your home with dated photos and video, keep a diary of the work and take advice before you appoint a surveyor or a solicitor. Speed matters, because every day of digging changes the evidence.

  • Talk first, then write. A short, polite letter or email asking them to pause and serve notice under the Act puts it on record.
  • Photograph everything. Cracks, doors that stick, the wall on your side, and the work you can see from your garden. Date every image.
  • Keep a diary. Note working hours, deliveries, vibration and any new damage.
  • Get the builder’s details. Their name, company and insurer will matter later.

Most building owners stop once they understand the risk. Many simply didn’t know the Act applied to their loft or extension.

Can a neighbour start building without a party wall notice?

Not lawfully, if the work is covered by the Act. Notice has to come before party wall work or nearby excavation. There’s no fine for skipping it, but the adjoining owner can ask a court to stop the work, and the building owner loses the rights and protection the Act would have given them.

The government’s party wall guidance lists the work that needs notice. It includes cutting into a party wall, removing a chimney breast from it and digging foundations within 3 or 6 metres of your building. The notice periods are set by section 3 and section 6: two months for party structure work, one month for excavation.

The explanatory booklet is clear that if work starts without notice, the adjoining owner can seek an injunction or other legal redress. Our guide to party wall agreements explains what the paperwork should have looked like.

No notice, no Act: what a Dagenham case decided

The leading case on this started with a chimney breast in a pair of semi-detached houses in Dagenham. The building owners removed it from the shared wall without serving notice. Removing a chimney breast is listed work under section 2 of the Act, so notice was needed.

Their neighbour said the work damaged his home. Surveyors were appointed and made an award in July 2018 setting out compensation. The building owners challenged it, arguing that no notice had ever been served, so the surveyors had no power to decide anything.

They won at every stage. The county court declared the award void, the High Court agreed, and in March 2023 the Court of Appeal dismissed the neighbour’s appeal in Power and Kyson v Shah. The dispute process in section 10 only applies once the Act has been brought into play. The phrase people now use for it is “no notice, no Act”.

The lesson for adjoining owners is uncomfortable. If your neighbour never served notice, appointing your own surveyor to make an award against them can waste money on a document a court may throw out. Your claim for damage still exists, but it sits in the courts, as nuisance or trespass, and not in the Act. If you live in Barking and Dagenham or anywhere else, take advice before you spend on surveyors.

Not sure what your project needs?

Send us the address and a line about the work. We’ll tell you what applies, how long it takes and what it costs.

Can you get a retrospective party wall agreement?

Partly. If work has started but isn’t finished, the building owner can serve notice now, and surveyors can make an award for the rest of the work. For work already completed without notice, an award is on shaky ground after the Dagenham ruling. Damage from that work becomes a civil claim.

In practice, the fix depends on how far the build has gone.

Work has only just started

The building owner pauses, serves the right notices and waits out the notice period, or agrees a shorter one in writing. Surveyors record the condition of your home before anything else happens. This is the cleanest outcome for both sides.

Work is well under way or finished

Both owners can agree in writing to have a surveyor record the current condition and settle what’s left. That agreement is a contract between you, not a statutory award, so get advice on the wording. Any damage already done is settled by negotiation or, failing that, a claim in court.

When does an injunction make sense?

An injunction makes sense when the work is ongoing, your home is at real risk and the building owner won’t stop and serve notice. A court can order the work to stop until the Act is followed. It’s expensive and slow to prepare, so it’s a backstop, used when a firm letter hasn’t worked.

Courts look at what’s at stake. A neighbour digging next to your foundations with no temporary support is a strong case. A neighbour fitting a kitchen is not. A solicitor will want your photos, your diary and your letters, which is why the first week matters so much.

A firm letter that mentions an injunction is often enough to bring the notice. Few building owners want their builder standing idle while a court decides.

What it costs

Expect substantial legal fees, even for an urgent hearing, and a costs risk if the court decides the application went too far. You may get your costs back if you win, but rarely all of them. Weigh that against the cost of repairing the damage you’re trying to prevent.

If you're the building owner who started early

Stop the party wall work and serve notice now. Every day you carry on adds risk: an injunction, a claim with no condition record to defend it against, and a neighbour who’ll be harder to deal with when you sell.

Then appoint a surveyor and get a schedule of condition of the neighbour’s home before work restarts. If your neighbour agrees, the surveyors can settle the remaining work in an award. Our guide to serving party wall notices explains what each notice must say.

Be straight with your neighbour about what’s already been done. If there’s damage, offer to put it right or pay for it. A neighbour who feels heard is far more likely to agree a short notice period than one who learns the facts from their own surveyor.

Talk to your builder too. A pause you choose now costs far less than one a court orders in month three.

Act in the first week, and keep a record

Three things decide how this ends. Speed, because evidence of your wall’s condition disappears as the work goes on. Paper, because letters and dated photos are what a surveyor or a court will rely on. And the right route, because since the Dagenham ruling an award against a neighbour who never served notice may not stand.

Most of these situations end with a late notice and a proper award, without anyone going to court. That only happens when someone moves quickly.

If work has started next door without notice, contact our party wall surveyors. We’ll tell you where you stand and what to send your neighbour, and we act across London and Essex.

Talk to a party wall surveyor

Send us the address, the drawings if you have them and a line about the work. We’ll tell you which notices apply, how long it takes and what it costs.

FAQ

More guides

3D model of a semi-detached house with its planned rear extension shown in blue

Party Wall

What is a party wall agreement, and when do you need one?

What a party wall agreement is, which work needs one, if it’s a legal requirement, how to get one and what happens if a neighbour refuses.
Two old houses joined by a shared wall, with bicycles parked outside

Party Wall

What is a party wall notice, and how do you serve one?

Which work needs a party wall notice, the notice period for each type, what a valid notice must include, how to serve it and what happens next.
All guides.

Contact Us

Get in touch.

Head Office
2-6 Boundary Row
London, SE1 8HP

Essex Office
2nd Floor, 10 High Street
Wickford, Essex
SS12 9AZ


020 3714 4090
enquiries@chpsurveyors.com